The Restaurant Accelerator
Want the restaurant to run without you? See what it takes.
Start your applicationHow long does it take from signing a lease to opening day?
In a worked example used to teach this plan, build-out runs thirteen weeks and training runs three weeks, so opening day lands sixteen weeks after the lease is signed.
The build-out, permits and inspections set the floor. The contractor's schedule sets the pace, not the owner's hopes. Training then runs three weeks in the new room, after the crew is hired. Thirteen plus three is sixteen weeks, and that number becomes the anchor for every other date on the plan.
In the worked example, a lease signed on March first produces an opening day of June twenty-first. Everything else, from when the crew is hired to when the soft open starts, is counted backward or forward from that single date.
What happens between opening day and day 90?
The room runs a soft open, then a grand opening, then ninety days of stabilizing until it runs on its own numbers without the opening team.
In the worked example, June twenty-first plus ninety days lands on September nineteenth, day ninety. That second date closes the plan. The soft open is invite only, with a short menu and a nightly debrief run by the new location's manager, not the owner. The grand opening follows once what broke in the soft open is fixed. From there the room stabilizes, trainers return home, and the location is expected to run on its own dashboard by day ninety.
Two dates, then, carry the whole plan: the opening date and day ninety. Every hire, every training week, every sign-off gets counted from one of those two.
Why does unit two take longer to open than later units?
Unit two has no existing playbook and no team already in their seats, so the opening needs its own dedicated team even while the first location keeps trading.
At a later unit, the playbook already exists and the people who run it are already in place. At unit two, the playbook is being written for the first time, while the first location still has to run normally every day. That's why the dated plan assigns a name to every step: an opening lead who owns the plan, a construction project manager for the build-out, a new manager hired well before opening, and specialists sent over to train the new crew.
Results are not typical and will vary with your business, your market, your team and how much of the work you actually do. Client figures on this site come from recorded interviews and are dated. Nothing here is a guarantee of revenue, profit or growth.
What does a month of delay actually cost?
In the worked example, a month of slip costs about fifteen thousand dollars in rent and manager payroll for a room that is not yet selling anything.
The worked numbers: rent of $120,000 a year is $10,000 a month, and a new manager hired at roughly $60,000 a year is $5,000 a month once they're on payroll. Add those together and a month of slip runs about $15,000, paid before the crew is even hired and before the room serves a single customer. That number is why the dated plan exists: it turns a vague sense of urgency into a figure an owner can actually weigh against a delay.
Should training be shortened if the build-out runs late?
No. When the build-out slips, the opening date should move, and the training period should not be cut short.
The pressure, when construction runs behind, is to protect the original opening date by trimming the three weeks of training. The plan says the opposite: let the opening date move. Training is the cheapest part of the whole plan, and an untrained crew produces bad reviews that do not disappear once the room is finally staffed properly.
What protects the locations that are already open while a new one launches?
A protection plan, reviewed on the regular weekly call, keeps the existing locations running on their numbers while the owner's attention is pulled toward the new opening.
The team, the dated plan and the protection plan all sit in the Opening Plan Workbook, and location two's targets go into the CEO Dashboard before it ever opens. The owner brings the plan to the weekly call along with the existing locations' managers, because the protection plan is theirs to run, not the owner's. A coach signs it off. The point is simple: attention spent fixing the new room by hand teaches the existing room to wait for the owner, and teaches the new room that the owner is the system instead of the process being the system.
Owners who want to see this dated plan used in real locations can look at case studies of owners who opened new units and changed what they needed to do day to day. Those thinking about what a new location actually costs before signing a lease may find it useful to read about what it costs to open a new restaurant location, line by line.

